Precedence diagram method
The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) in 2009 suggests that the term ‘precedence diagram method’, or PDM, refers to:
A method of constructing a logic network using nodes to represent the activities and connecting them by lines that show dependencies.
The Precedence Diagramming Method (PDM) is a visual representation technique which is used to prepare the project schedule network diagrams and determine the critical path.
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, suggest that a precedence diagram is a network in which the nodes symbolise activities, also referred to as an 'activity-on-the-node network'.
[edit] Related articles on Designing Buildings Wiki
- Acceleration.
- Accepted programme.
- Activity schedule.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Gantt chart.
- Information release schedules.
- Milestones.
- Programme consultant.
- Programme float.
- Programme for building design and construction
- Scheduling construction activities.
- Short period programme.
- Time-location chart.
[edit] External references
Featured articles and news
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
Comments
Will any one answer me if I post a comment
That depends what the comment is.