Precedence diagram method
The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) in 2009 suggests that the term ‘precedence diagram method’, or PDM, refers to:
A method of constructing a logic network using nodes to represent the activities and connecting them by lines that show dependencies.
The Precedence Diagramming Method (PDM) is a visual representation technique which is used to prepare the project schedule network diagrams and determine the critical path.
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, suggest that a precedence diagram is a network in which the nodes symbolise activities, also referred to as an 'activity-on-the-node network'.
[edit] Related articles on Designing Buildings Wiki
- Acceleration.
- Accepted programme.
- Activity schedule.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Gantt chart.
- Information release schedules.
- Milestones.
- Programme consultant.
- Programme float.
- Programme for building design and construction
- Scheduling construction activities.
- Short period programme.
- Time-location chart.
[edit] External references
Featured articles and news
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
Comments
Will any one answer me if I post a comment
That depends what the comment is.